Pakal Dul Hydroelectric Project, Jammu and Kashmir (India)

  • 05/04/2021
  •  

Bauer has been commissioned with the execution of the following:

 

  • Plastic concrete cut-off wall (width: 1.0 m): total length in plan view is 150 m, maximum depth approx. 70m, with an expected area of about 8500 m²
  • Pre-Treatment along the cutoff wall alignment

 

Execution period:

Start: October 2021
Duration: 10 months after full mobilization (expected project completion: mid-2022)

 

The project is being located on the Marusadar River, a tributary of the Chenab River in Kishtwar district of the Indian Jammu and Kashmir. The primary purpose of the dam is hydroelectric power generation.